Please read a further update below from South East Water, issued on 12/11/21.

Project updates

November 12, 2021

Following a successful drop-in session with residents in Elvetham Heath and discussions with Hartley Wintney Parish Council, we have made some amendments to our program.

Work is still planned to begin in Fleet Road later this month however we will be starting at its junction with Pale Lane, working towards Reading Road.

This first section will be carried out using temporary traffic lights in order to minimise disruption to the local community.

Work will continue until 12 December, at which point all works in Fleet Road will stop as agreed by Hampshire Highways. This is to ensure we avoid causing disruption during the busy festive period.

Our workforce will return to Fleet Road on 10 January 2022, at which point a road closure will be in place.

We’re very sorry for any disruption this may cause and we are really grateful for your continued patience while we carry out this vital work.